                KRECO Engineering Change & Technical Modification Policy
                Publish Date:2017-05-24    Click:234


                Policy on Technical Modifications & Specification Control

                To ensure product reliability and regulatory compliance (e.g., IEC 60601, 62368), KRECO enforces a strict Engineering Change Order (ECO)​ protocol.
                All modifications must be documented and mutually confirmed before mass production commences.


                No.
                Policy Item

                Detailed Terms & Conditions

                1​
                Formal Change Request (ECR)​

                All technical adjustments must be submitted via official email.
                Our engineering team will update the Specification for Approval Sheet​ accordingly.

                2​
                Non-Conformance Liability​

                If KRECO's samples fail internal QC or industry standard testing due to our manufacturing defect, we shall bear the cost of replacement samples and prepaid freight for re-evaluation.

                3​
                Technical Freeze & Sign-off​

                Mandatory Authorization.

                Mass production will not be scheduled until the revised Specification for Approval Sheet​ is formally signed and stamped by an authorized representative of your company.

                4​
                Lead Time Recalculation​

                The production lead time is contingent upon the final sign-off date. KRECO requires confirmation within 3 business days;
                failure to respond promptly will result in automatic rescheduling of your order.

                5​
                Mid-Production Changes​

                Should KRECO initiate a technical change during production (e.g., component obsolescence), we will issue a Technical Change Notice (TCN).
                Customer approval is required within 3 business days to avoid production halts.

                6​
                Golden Sample Reference​

                All mass-produced goods will strictly adhere to the parameters of the Customer-Approved Golden Sample.

                7​
                Delivery Schedule Integrity​

                Requests to expedite delivery beyond the confirmed lead time will not be accepted once the production plan is locked.


                Disclaimer:
                ​ KRECO reserves the right to amend or update these technical policies without prior notice. The latest version is binding.